Excusable, but non-compensable delays are:

Prepare for the CMAA Construction Management Exam. Study with flashcards and multiple choice questions, each question includes hints and explanations. Get exam-ready now!

Multiple Choice

Excusable, but non-compensable delays are:

Explanation:
Excusable delays that are noncompensable occur when the delay stems from events outside anyone’s control, so the contractor gets more time but no extra payment. If the delay is beyond the owner’s control, it isn’t the contractor’s fault and the contract typically allows a time extension without additional costs being paid to the contractor. That’s why delays caused by factors outside the owner’s control fit this category. Delays within the owner’s control aren’t excusable in this sense because the owner’s actions can be managed or avoided, so they don’t justify noncompensable extensions. Owner changes (change orders) and differing site conditions usually involve some form of cost adjustment or at least a potential for compensation, rather than being strictly noncompensable extensions.

Excusable delays that are noncompensable occur when the delay stems from events outside anyone’s control, so the contractor gets more time but no extra payment. If the delay is beyond the owner’s control, it isn’t the contractor’s fault and the contract typically allows a time extension without additional costs being paid to the contractor. That’s why delays caused by factors outside the owner’s control fit this category.

Delays within the owner’s control aren’t excusable in this sense because the owner’s actions can be managed or avoided, so they don’t justify noncompensable extensions. Owner changes (change orders) and differing site conditions usually involve some form of cost adjustment or at least a potential for compensation, rather than being strictly noncompensable extensions.