For a large program described as using the multiple-prime method, which procurement approach is used?

Prepare for the CMAA Construction Management Exam. Study with flashcards and multiple choice questions, each question includes hints and explanations. Get exam-ready now!

Multiple Choice

For a large program described as using the multiple-prime method, which procurement approach is used?

Explanation:
The key idea is that a multiple-prime procurement approach involves awarding several prime contracts to different firms for distinct portions of the project, rather than one contract covering everything. When a large program is described as using the multiple-prime method, it means the owner coordinates separate contracts—often including design services and multiple construction packages—so work can proceed in parallel and specialists can be brought in for each portion. This setup can speed delivery and give the owner more control over who performs each piece, but it requires careful coordination and interface management across all contracts. This approach differs from design-bid-build, which typically uses a single general contractor after separate design work, from design-build, which bundles design and construction under one contract, and from Construction Manager at Risk, where a CM acts as the single manager/contractor with a guaranteed maximum price. So the procurement approach used is the multiple-prime method.

The key idea is that a multiple-prime procurement approach involves awarding several prime contracts to different firms for distinct portions of the project, rather than one contract covering everything. When a large program is described as using the multiple-prime method, it means the owner coordinates separate contracts—often including design services and multiple construction packages—so work can proceed in parallel and specialists can be brought in for each portion. This setup can speed delivery and give the owner more control over who performs each piece, but it requires careful coordination and interface management across all contracts. This approach differs from design-bid-build, which typically uses a single general contractor after separate design work, from design-build, which bundles design and construction under one contract, and from Construction Manager at Risk, where a CM acts as the single manager/contractor with a guaranteed maximum price. So the procurement approach used is the multiple-prime method.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy