In scheduling terminology, which method represents activities on nodes and is commonly used with dependency types such as finish-to-start?

Prepare for the CMAA Construction Management Exam. Study with flashcards and multiple choice questions, each question includes hints and explanations. Get exam-ready now!

Multiple Choice

In scheduling terminology, which method represents activities on nodes and is commonly used with dependency types such as finish-to-start?

Explanation:
Activities on nodes is the approach that places each activity as a node, with the sequencing relationships drawn between those nodes. This is the contemporary way to diagram schedules, known as the Activity-on-Node representation and it underpins the Precedence Diagramming Method. It naturally accommodates multiple dependency types, including finish-to-start (one activity must finish before the next starts) as well as start-to-start, finish-to-finish, and start-to-finish. The other common diagramming method places activities on arrows, which is less flexible for expressing these varied dependencies. So the correct concept is Activity-on-Node.

Activities on nodes is the approach that places each activity as a node, with the sequencing relationships drawn between those nodes. This is the contemporary way to diagram schedules, known as the Activity-on-Node representation and it underpins the Precedence Diagramming Method. It naturally accommodates multiple dependency types, including finish-to-start (one activity must finish before the next starts) as well as start-to-start, finish-to-finish, and start-to-finish. The other common diagramming method places activities on arrows, which is less flexible for expressing these varied dependencies. So the correct concept is Activity-on-Node.