What is the range of accuracy for an Order of Magnitude estimate?

Prepare for the CMAA Construction Management Exam. Study with flashcards and multiple choice questions, each question includes hints and explanations. Get exam-ready now!

Multiple Choice

What is the range of accuracy for an Order of Magnitude estimate?

Explanation:
Order of Magnitude estimates are rough, early-stage cost guesses made with limited information. Because many unknowns exist—design scope, site conditions, inflation, labor rates—the expected accuracy is wide. The standard range is approximately +50% to -30% of the final cost, meaning the forecast could be as high as 1.5x or as low as 0.7x the actual cost. This level is used to screen options and decide whether to invest in more detailed studies; it is not a commitment. Other ranges are either too narrow for this stage or imply more precision than is typical at this point.

Order of Magnitude estimates are rough, early-stage cost guesses made with limited information. Because many unknowns exist—design scope, site conditions, inflation, labor rates—the expected accuracy is wide. The standard range is approximately +50% to -30% of the final cost, meaning the forecast could be as high as 1.5x or as low as 0.7x the actual cost. This level is used to screen options and decide whether to invest in more detailed studies; it is not a commitment. Other ranges are either too narrow for this stage or imply more precision than is typical at this point.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy