Which metric is the difference between BCWP and BCWS?

Prepare for the CMAA Construction Management Exam. Study with flashcards and multiple choice questions, each question includes hints and explanations. Get exam-ready now!

Multiple Choice

Which metric is the difference between BCWP and BCWS?

Explanation:
In earned value management, BCWP is the value of work actually completed, and BCWS is the value of work that was planned to be completed by this point, both based on budgeted cost. The difference between them is Schedule Variance, calculated as Schedule Variance = BCWP − BCWS. A positive variance means you’ve earned more value than was planned (ahead of schedule), while a negative variance means you’re behind. For context, other metrics use different formulas: Cost Variance is BCWP − AC (earned value minus actual cost), CPI is EV/AC, and SPI is EV/PV. But the specific difference between BCWP and BCWS is Schedule Variance.

In earned value management, BCWP is the value of work actually completed, and BCWS is the value of work that was planned to be completed by this point, both based on budgeted cost. The difference between them is Schedule Variance, calculated as Schedule Variance = BCWP − BCWS. A positive variance means you’ve earned more value than was planned (ahead of schedule), while a negative variance means you’re behind.

For context, other metrics use different formulas: Cost Variance is BCWP − AC (earned value minus actual cost), CPI is EV/AC, and SPI is EV/PV. But the specific difference between BCWP and BCWS is Schedule Variance.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy