Which statement correctly describes the critical path in a project network?

Prepare for the CMAA Construction Management Exam. Study with flashcards and multiple choice questions, each question includes hints and explanations. Get exam-ready now!

Multiple Choice

Which statement correctly describes the critical path in a project network?

Explanation:
The critical path is the sequence of activities that determines the project’s duration. It is the longest path through the activity network, measured by total duration, so it sets the minimum time required to complete the project. Any delay on this path delays the entire project because those activities have no flexibility to slip without affecting the finish date. Other paths have slack, meaning they can be delayed without extending the project deadline. The critical path typically has zero total slack, and it may be one or more paths if several routes share the same maximum duration.

The critical path is the sequence of activities that determines the project’s duration. It is the longest path through the activity network, measured by total duration, so it sets the minimum time required to complete the project. Any delay on this path delays the entire project because those activities have no flexibility to slip without affecting the finish date. Other paths have slack, meaning they can be delayed without extending the project deadline. The critical path typically has zero total slack, and it may be one or more paths if several routes share the same maximum duration.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy