Which statement describes the traditional delivery system as NOT being traditional?

Prepare for the CMAA Construction Management Exam. Study with flashcards and multiple choice questions, each question includes hints and explanations. Get exam-ready now!

Multiple Choice

Which statement describes the traditional delivery system as NOT being traditional?

Explanation:
In CMAA terms, the traditional delivery system is design-bid-build, typically executed in a linear sequence with clear separation of roles among the owner, designer, and contractor. The statement presented says that the “design-build-build operate” system remains the most popular delivery method. That wording points to a non-traditional approach (design-build-operate) being the dominant method, which means the traditional system isn’t being used in its conventional sense. This is why it’s the best answer: it explicitly describes a non-traditional method as the prevailing approach, effectively implying that traditional delivery is not traditional in practice. The other statements describe aspects that align with the traditional model—linear progression of major phases, the owner-designer-contractor arrangement with subcontractors, and design-bid-build remaining the most popular—so they don’t describe the traditional system as not traditional.

In CMAA terms, the traditional delivery system is design-bid-build, typically executed in a linear sequence with clear separation of roles among the owner, designer, and contractor. The statement presented says that the “design-build-build operate” system remains the most popular delivery method. That wording points to a non-traditional approach (design-build-operate) being the dominant method, which means the traditional system isn’t being used in its conventional sense. This is why it’s the best answer: it explicitly describes a non-traditional method as the prevailing approach, effectively implying that traditional delivery is not traditional in practice. The other statements describe aspects that align with the traditional model—linear progression of major phases, the owner-designer-contractor arrangement with subcontractors, and design-bid-build remaining the most popular—so they don’t describe the traditional system as not traditional.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy